Project TimelineProjects vary dramatically in
size, scope and complexity. Even so, all of our project timetables are tailored
to meet your needs (you may have specific target dates for completion). We are
flexible in the design process to meet those needs. Our design schedule is
arranged around your work, vacation and travel schedule.
Standard Project Timetable
|
Phase |
Time Frame |
| Programming and Fact Gathering |
1-2 Weeks |
| Conceptual Design |
1-2 Weeks |
| Design Development |
2-3 Weeks |
| Bidding |
0-1 Week |
| Construction (Dependent upon complexity of project) |
Variable (1-8 Weeks) |
| Standard Project Timeline |
1-6 months |
The most unpredictable part of the timetable is the contractor's availability
to start work. There is often a waiting period of two to eight weeks in which
the contractor finishes other work he has previously committed to. While overall
project timetables vary considerably from our first meeting until completion of
construction, they usually take a minimum of three months and often take six
months. Early spring and late autumn projects may take longer to accomplish, due
to inclement weather, but an advantage is that the contractor-waiting period is
often shorter.
Design Department Links
|