Project Timeline

Projects vary dramatically in size, scope and complexity. Even so, all of our project timetables are tailored to meet your needs (you may have specific target dates for completion).   We are flexible in the design process to meet those needs.  Our design schedule is arranged around your work, vacation and travel schedule.

Standard Project Timetable

Phase Time Frame
Programming and Fact Gathering 1-2 Weeks
Conceptual Design 1-2 Weeks
Design Development 2-3 Weeks
Bidding 0-1 Week
Construction (Dependent upon complexity of project) Variable (1-8 Weeks)
Standard Project Timeline 1-6 months

The most unpredictable part of the timetable is the contractor's availability to start work. There is often a waiting period of two to eight weeks in which the contractor finishes other work he has previously committed to. While overall project timetables vary considerably from our first meeting until completion of construction, they usually take a minimum of three months and often take six months. Early spring and late autumn projects may take longer to accomplish, due to inclement weather, but an advantage is that the contractor-waiting period is often shorter.


Design Department Links





 
image